$4237 of new work, bring the total contract amount to $107,866 (plus tax). This is under the $160,000 county cost estimate for the work and is reimbursable within the appropriation from the state Housing Trust Fund.
Type: Deliberation
Department: CF - Capital Facilities
Directors' Update: April 9, 2025
Business Meeting: April 15, 2025
Summary:Ratify two change orders for the Lewis County Permanent Shelter Renovations contract with Schwiesow Construction, Inc., Project #31-2408 Construction, relating to work identified in closing out the renovations
Publications:
Cover Letter To:
Additional Copies To:
Resolution
RATIFY A CHANGE ORDER FOR THE LEWIS COUNTY PERMANENT SHELTER RENOVATIONS CONTRACT WITH SCHWIESOW CONSTRUCTION INC., PROJECT #31-2408 CONSTRUCTION, RELATING TO WORK IDENTIFIED IN CLOSING OUT THE RENOVATIONS
WHEREAS, Lewis County is renovating 2015 NE Kresky Ave., Chehalis, into a permanent night-by-night shelter for people experiencing homelessness, and has received a direct appropriation from the state Housing Trust Fund for that purpose; and
WHEREAS, Lewis County previously published a formal call for bids for shelter renovation and awarded that contract to Schwiesow Construction as the lowest bidder, at a cost well under the county's cost estimate; and
WHEREAS, in making those renovations, certain needed work was identified to close out the renovations: (1) minor HVAC repairs needed for the project's HVAC extension to function, and (2) a code-required plumbing change to a part of the building not otherwise part of the project; and
WHEREAS, the Director of Facilities signed Change Orders 5 and 6 for $4237 for this work, bringing the total contract amount to $107,866 plus tax (which remains within budget and well under the $160,000 county estimate for the renovations contract).
NOW THEREFORE BE IT RESOLVED that the Board of County Commissioners ratifies Change Orders 5 and 6 with Schwiesow Construction Inc. for the above work on the Lewis County Permanent Shelter renovations project, Project #31-2408 Construction.
DONE IN OPEN SESSION this 15th day of April, 2025.