Information
Type: Deliberation
Department: CI - Capital Infrastructure
Directors' Update: Dec. 31, 2025
Business Meeting: Jan. 6, 2026
Summary:Approve contract with Elite Mechanical Services LLC for Law and Justice Boiler Replacement Project
Publications:
Cover Letter To:
Additional Copies To:
Resolution
APPROVE CONTRACT WITH ELITE MECHANICAL SERVICES LLC FOR LAW AND JUSTICE BOILER REPLACEMENT PROJECT
WHEREAS, the Lewis County Board of County Commissioners (BOCC) issued a request for proposals (RFP) for the removal and replacement of boilers at the Law and Justice building via Resolution 25-298; and
WHEREAS, the Capital Infrastructure Specialist issued the RFP on October 28, 2025, with proposals due December 1, 2025; and
WHEREAS, the Capital Infrastructure Specialist received proposals from the four following firms:
- Elite Mechanical Services LLC
- Copper Mechanical
- Apex Mechanical LLC
- NW Thermal Hydronics LLC
WHEREAS, the Capital Infrastructure Specialist has determined that Elite Mechanical Services LLC's proposal was the lowest responsive bid, and the BOCC approved awarding the contract to Elite via Resolution 25-368.
NOW THEREFORE BE IT RESOLVED that the BOCC hereby approves the contract with Elite Mechanical Services LLC in the amount of $345,685.65 (including taxes) for the Law and Justice Boiler replacement and ratifies the signature of Capital Infrastructure Specialist Matt Patana on said contract, attached hereto as Exhibit A; and
NOW THEREFORE BE IT FURTHER RESOLVED the contract will extend from January 15, 2026, through April 1, 2026, and funding will come from REET 1, funding source 3110.
DONE IN OPEN SESSION this 6th day of January, 2026.