Contract Award for the L&J Exterior Upgrades Project

Publications:

Cover Letter To:

Additional Copies To:

Resolution

Wording/In the matter of:

AWARDING A CONTRACT FOR THE LAW AND JUSTICE EXTERIOR UPGRADES PROJECT, PROJECT #31-2026

Resolution Number: 21-172

WHEREAS, the south elevation of the Law & Justice Center suffered water intrusion and damage to the Exterior Finish and Insulation System (EFIS) cladding causing the system to begin to separate from the building and create a potential hazard; and

WHEREAS, plans and specifications were developed by KMB Architects to remove and replace the EIFS cladding on the south face of the building and paint the building exterior; and

WHEREAS, a Call for Bids was issued for the project on March 16, 2021 and the responses were as follows:

Rognlin's, Inc   Aberdeen, WA                  $502,500.00

JA Morris Construction   Olympia, WA     $411,000.00

Schwiesow Construction   Centralia, WA  $399,000.00; and

WHEREAS, Schwiesow Construction appears to have submitted the lowest responsive bid.

NOW THEREFORE BE IT RESOLVED that the contract for the L&J Exterior Upgrades Project be awarded to Schwiesow Construction of Centralia, WA for $399,000.00; and

NOW THEREFORE BE IT FURTHER RESOLVED that the Chief of Internal Services be authorized to sign said contract on behalf of the Board of County Commissioners.

DONE IN OPEN SESSION this 27th day of April, 2021.