Information
$39,500; plus tax and permit fees for initial bid; Change order adds $24,500 for a total of $64,000 plus tax and permit fees; Capital Budget State grant funds.
Type: Deliberation
Department: CF - Capital Facilities
Directors' Update: Jan. 15, 2025
Business Meeting: Jan. 21, 2025
Summary:Ratify signature for the Toledo Senior Center Roof replacement contract and subsequent change order.
Publications: N/a
Cover Letter To:
Additional Copies To:
Resolution
RATIFY SIGNATURE FOR THE TOLEDO SENIOR CENTER ROOF REPLACEMENT CONTRACT AND APPROVE ONE SUBSEQUENT CHANGE ORDER, PROJECT 31-2417
WHEREAS, the Facilities Department has determined the roof on the Toledo Senior Center Building is in need of replacement; and
WHEREAS, a bid call was issued using the Small Works roster process on November 19, 2024, and the responses were as follows:
| COMPANY | BID AMOUNT | |
| Safecover Roofing LLC | $39,500.00 | |
| Coastline Roofing and Construction Inc. | $49,000.00 |
WHEREAS, Safecover Roofing has submitted the lowest responsible bid of $39,500.00 plus tax and permit fees; and
WHEREAS, pursuant to Resolution 23-232, the BOCC defines "Agreement" as a contract that binds Lewis County to a course of action, such as change orders, grant applications or contract amendments; and
WHEREAS, An additional change order is needed in the amount of $24,500; and
WHEREAS, Resolution 23-232 further stipulates for agreements that total - or create a cumulative project total of $50,000 to $350,000, department heads must receive BOCC approval via resolution for agreements that total - or increase the cumulative project total to -- $50,000 to $350,000.
NOW THEREFORE BE IT RESOLVED the Board of County Commissioners hereby ratifies the signature of the Capital Facilities Manager on the contract with Safecover Roofing LLC - in the amount of $39,500.00 plus tax and permit fees - to complete the Roof Replacement Project; and
NOW THEREFORE BE IT FURTHER RESOLVED the Board of County Commissioners hereby ratifies the signature of the County Manager on the accompanying change order for $24,500.00 plus tax and permit fees for a contract total of $64,000, plus tax and permit fees for Project 31-2417, Toledo Senior Center Roof Replacement.
DONE IN OPEN SESSION this 21st day of January, 2025.