Directors' Update: June 16, 2021
Business Meeting: June 22, 2021
Summary:Due to a series of high water events occurring in January 2021 it has become necessary to do bank stabilization work along Newaukum Valley Road, between MP 1.085-1.105. The project will require additional road right of way from one property owner. RCW Chapter 8 authorizes Counties to acquire property when deemed necessary by the Board of County Commissioners. Pursuant to the requirements of RCW Chapter 8, this resolution instructs the County Engineer to acquire right of way from one property owner along Newaukum Valley Road for the project. All such acquisitions shall be in accordance with adopted procedures as per Resolution 20-149.
Publications:
Cover Letter To:
Additional Copies To: Kim Amrine, Tim Fife, Martin Roy, Kelly Albert, Tina Hemphill
Resolution
THE PROPOSED ACQUISITION OF ADDITIONAL RIGHT OF WAY FOR NEWAUKUM VALLEY ROAD, CHEHALIS
WHEREAS, It has become necessary to do bank stabilization work on Newaukum Valley Road between Mile Post (MP) 1.085-1.105; and
WHEREAS, the bank stabilization project is necessary to protect the county road and will benefit the public; and
WHEREAS, the project will require additional right of way from one adjacent property owner; and
WHEREAS, RCW 8.08.010 authorizes counties to acquire property when deemed necessary by the BOCC; and
WHEREAS, pursuant to the requirements of RCW 8.08, this resolution instructs the County Engineer to acquire right of way as shown on the attached exhibit from one property owner along Newaukum Valley Road for the project.
NOW THEREFORE BE IT RESOLVED that the County Road Engineer is instructed to acquire all necessary right of way and is authorized to sign documents necessary for the bank stabilization project on Newaukum Valley Road in Section 16, Township 13 North, Range 2 West, W.M.
DONE IN OPEN SESSION this 22nd day of June, 2021.