This resolution will approve consultant supplements over $50,000 for the consultant contract with Northwest Hydraulic Consultants Inc. 

 

Publications:

Cover Letter To:

Additional Copies To: Kim Amrine-PW, Rose Williams-PW, Geoff Soderquist, PW, Ann Weckback, PW

Resolution

Wording/In the matter of:

APPROVAL OF CONSULTANT SUPPLEMENTS OVER $50,000 FOR THE ANNUAL HYDROLOGIC, HYDRAULIC, AND GEOMORPHIC CONSULTANT CONTRACT WITH NORTHWEST HYDRAULIC CONSULTANTS INC.

Resolution Number: 21-153

WHEREAS, pursuant to Resolution 21-038, Board of County Commissioners (BOCC) approval is required for all contracts, projects, agreements, grant applications, contract amendments and change orders involving expenditures totaling between $50,000 and $200,000; and

WHEREAS, Resolution 21-007 was approved by the BOCC which ratified a consultant agreement and Supplement #1 and #2 with Northwest Hydraulic Consultants, Inc.; and

WHEREAS, Resolution 21-071 was approved by the BOCC which ratified Supplement #3 with Northwest Hydraulic Consultants, Inc.; and

WHEREAS, Supplement #4 was executed by the Public Works Director on March 23, 2021 to accommodate a new anticipated task order in the amount of $200,000, for analyses and design of the Newaukum Valley Rd Bank Stabilization project which increased the contract amount from $532,000 to $732,000; and

WHEREAS, Supplement #5 is needed for an additional task orders for design of the Kiona Rd Revetment Replacement in the amount of $500,000; hydrologic and hydraulic analyses and design of Shorey Rd Bank Stabilization; and hydrologic and hydraulic analyses and design of the Pigeon Springs Rd Bank Stabilization project and will increase the contract total amount from $732,000 to $1,232,000.

NOW THEREFORE BE IT RESOLVED that Supplement #4 previously executed by Public Works is hereby approved by the Board of County Commissioners; and

NOW THEREFORE BE IT FURTHER RESOLVED that Supplement #5 is hereby approved by the Board of County Commissioners.