A Call for Bids for the South Lewis County Airport (TDO) Improvements Project, A.I.P. 3-53-0078-009-2017 was made on February 3, 2020. The project was advertised in the Chronicle, the Seattle Daily Journal of Commerce, and Lewis County's website. Public Works received 8 bids for this project February 25, 2020. Sterling Breen Crushing, Inc. provided the lowest responsive bid of $3,040,973.32. The engineer's estimate was $2,734,888.70. Public Works staff recommends acceptance of the low bid provided by Sterling Breen Crushing, Inc.

Publications:

Cover Letter To:

Additional Copies To: John Roe, Tina Hemphill, Robin Saline, Rose Williams, PW

Resolution

Wording/In the matter of:

LISTING OF BIDS AND CONTRACTOR SELECTED FOR THE SOUTH LEWIS COUNTY AIRPORT (TDO) IMPROVEMENTS PROJECT, A.I.P. 3-53-0078-009-2017

Resolution Number: 20-089

WHEREAS, pursuant to Resolution 20-041, a call for bids was issued on February 2, 2020, for the South Lewis County Airport (TDO) Improvements Project, A.I.P. 3-53-0078-009-2017; and

WHEREAS, bid quotations have been submitted from contractors as follows:

Contractor Name City, State Bid Amount
Sterling Breen Crushing, Inc. Centralia, WA $3,040,973.32
Tapani, Inc. Battleground, WA $3,052,971.46
Boettcher & Sons Eatonville, WA $3,449,947.92
Midway Underground Toledo, WA $3,504,696.58
Rognlin's, Inc. Aberdeen, WA $3,696,408.10
JH Kelly Longview, WA $3,712,491.86
Northwest Cascade, Inc. Puyullap, WA $4,227,053.60
Nordland Construction Nordland, WA $4,434,784.20

WHEREAS, Sterling Breen Crushing, Inc. provided the lowest responsive bid quote of $3,040,973.32 for the South Lewis County Airport (TDO) Improvements Project, A.I.P. 3-53-0078-009-2017.

NOW THEREFORE BE IT RESOLVED that the contract for the South Lewis County Airport (TDO) Improvements Project, A.I.P. 3-53-0078-009-2017 shall be awarded to Sterling Breen Crushing, Inc. in the amount of $3,040,973.32 upon the execution of a contract acceptable to the Board of County Commissioners (BOCC). Upon presentation of such a contract, the Public Works Director is authorized to sign on behalf of the BOCC.