Proposal

Information

Roads - Contract: $2,108,853.75

Type: Deliberation

Department: PW - Public Works

Directors' Update: June 18, 2025

Business Meeting: June 24, 2025

Summary:

A call for bids for the Van Ornum Creek @ Bunker Creek Road MP 2.681 Culvert Removal,  F.A. PROTECT-21AD(001), CMP-1610 was issued on May 7, 2025. Public Works received three responsive bids on May 29, 2025.  The engineer's estimate is $1,883,676.80.

Public Works recommends awarding this project to the lowest responsible and responsive bidder, Midway Underground LLC, Toledo, Washington

Publications:

Cover Letter To:

Additional Copies To: Robin Saline, Eena Wiest, Geoff Soderquist, Wes Anderson, Tina Correia, Zelma Hammer; PW

Resolution

Wording/In the matter of:

LIST THE BIDS RECEIVED AND CONTRACTOR SELECTED FOR THE VAN ORNUM CREEK @ BUNKER CREEK ROAD MP 2.681 CULVERT REMOVAL, F.A. PROTECT-21AD(001), CMP-1610

Resolution Number: 25-175

WHEREAS, a call for bids was issued May 7, 2025, for the Van Ornum Creek @ Bunker Creek Road MP 2.681 Culvert Removal, F.A. PROTECT-21AD(001), CMP-1610; and

WHEREAS, bid quotations were submitted from the contractors as follows:

CONTRACTOR LOCATION TOTAL COST
Midway Underground LLC

Toledo, WA $2,108,853.75
Rognlin's Inc. Aberdeen, WA

$2,114,370.00

Mike McClung Construction Buckley, WA

$2,127,470.00

     

WHEREAS, Midway Underground LLC provided the lowest responsive bid quote for the Van Ornum Creek @ Bunker Creek Road MP 2.681 Culvert Removal, F.A. PROTECT-21AD(001), CMP-1610.

NOW THEREFORE BE IT RESOLVED that the contract for the Van Ornum Creek @ Bunker Creek Road MP 2.681 Culvert Removal, F.A. PROTECT-21AD(001), CMP-1610 shall be awarded to Midway Underground LLC in the amount of $2,108,853.75. Upon presentation of a contract, the County Engineer is authorized to sign on behalf of the BOCC.

DONE IN OPEN SESSION this 24th day of June, 2025.