Proposal

Information

Type: Legal Notice

Department: PW - Public Works

Directors' Update: April 9, 2025

Business Meeting: April 15, 2025

Summary:

Publication of 2024 County Forces road construction projects and costs

Publications: The East County Journal on April 16

Cover Letter To:

Additional Copies To: Geoff Soderquist-PW, Wes Anderson-PW, Mike Kroll-PW, Tina Hemphill-PW

Resolution

Wording/In the matter of:

PUBLICATION OF 2024 COUNTY FORCES ROAD CONSTRUCTION PROJECTS AND COSTS

Resolution Number: 25-108

WHEREAS, pursuant to RCW 36.77.070, construction completed by county forces, where the cost of the work exceeds $10,000, must be published in one issue of a newspaper of general circulation in the county with a brief description of the work, together with the true and complete cost of performing such construction by county forces; and

WHEREAS, construction by county forces is defined in WAC 136-18-020 as construction work performed by personnel carried on the county payroll using county owned, leased or rented equipment.

NOW THEREFORE BE IT RESOLVED by the Board of County Commissioners that the following road construction was completed by county forces in the calendar year 2024 at the cost shown and is hereby directed to be published in compliance with RCW 36.77.070. Costs shown do not include engineering, right of way charges, or county forces expenditures less than $10,000.

 

CRP NO. NAME OF PROJECT COUNTY FORCES COSTS
2207 Countywide 3R Program $460,232
  *TOTAL   $460,232


* “TOTAL” includes only those 2024 projects that exceed $10,000 in county forces expenditures.

DONE IN OPEN SESSION this 15th day of April, 2025.