Information
Type: Deliberation
Department: PW - Public Works
Directors' Update: May 15, 2024
Business Meeting: May 21, 2024
Summary:The Meade Hill Road Stabilization project, SM 21F754500077, funded by the FEMA Public Assistance Program, requires additional right of way for stabilization of the road. The project will require temporary construction easements from two property owners. This resolution instructs the County Engineer to acquire the necessary right of way from two property owners along Meade Hill Road for the project.
Publications:
Cover Letter To:
Additional Copies To: Tina Hemphill Robin Saline
Resolution
THE PROPOSED ACQUISITION OF RIGHT OF WAY FOR THE MEADE HILL ROAD STABILIZATION PROJECT, SM 21F754500077
WHEREAS, stabilization of Meade Hill Road is needed between MP 0.77-MP 0.815 due to a slide; and
WHEREAS, the proposed work will require temporary construction easements from two adjoining owners; and
WHEREAS, this project is priority number 4 within the adopted and amended 2024-2029 Six-Year Transportation Improvement Program; and
WHEREAS, this project is a necessary improvement and will benefit the public; and
WHEREAS, this resolution instructs the County Engineer to acquire additional right of way as shown on the attached Exhibit from two property owners along Meade Hill Road.
NOW THEREFORE BE IT RESOLVED that the County Engineer is instructed to acquire all right of way necessary for the stabilization of Meade Hill Road in Section 13, Township 12N, Range 5 East W.M., SM 21F754500077, and directs that the acquisition shall be in accordance with adopted procedures per Resolution 20-149.
DONE IN OPEN SESSION this 21st day of May, 2024.