Proposal

Information

$179,689.00

Type: Deliberation

Department: PW - Public Works

Directors' Update: March 27, 2024

Business Meeting: April 2, 2024

Summary:

This resolution will ratify a contract amendment that cumulatively increases a contract's maximum amount payable by $179,689.00, thus bringing the maximum amount payable for the Packwood Sewer System Project consultant agreement with HDR to $4,166,728.00.

 

Publications:

Cover Letter To:

Additional Copies To: Tina Hemphill, Robin Saline, Geoff Soderquist, Wes Anderson, Mark Burch, PW

Resolution

Wording/In the matter of:

RATIFY A CONTRACT AMENDMENT WITH HDR FOR THE PACKWOOD SEWER SYSTEM PROJECT

Resolution Number: 24-100

WHEREAS, pursuant to Resolution 23-233, subsequent change orders or amendments to procurement contracts, originally approved by a Director, must receive BOCC approval via resolution before entering into agreements that exceed $350,000 or increase the cumulative total to more than $350,000; and

WHEREAS, approval of Amendment No. 1 is needed to increase the Packwood Sewer System project maximum amount payable by $179,689.00, to a new maximum amount payable of $4,166,728.00, to provide additional Environmental Site Assessment support to Lewis County for the Packwood Sewer System project as stated in Subtask 604.

NOW THEREFORE BE IT RESOLVED that Amendment No. 1 to the Packwood Sewer System agreement with HDR is ratified, bringing the total value to $4,166,728.00, and the Public Works Director is hereby authorized to sign the same.

DONE IN OPEN SESSION this 2nd day of April, 2024.