Information
Type: Deliberation
Department: PW - Public Works
Directors' Update: Nov. 22, 2023
Business Meeting: Nov. 28, 2023
Summary:The Shorey Road Bank Stabilization project, which is funded by the FHWA Emergency Relief Program (ER), requires additional right of way for stabilization of the road. The project will require additional right of way from one property owner. This resolution instructs the County Engineer to acquire the necessary right of way from one property owner.
Publications:
Cover Letter To:
Additional Copies To: Tina Hemphill Shawn Kyes
Resolution
THE PROPOSED ACQUISITION OF ADDITIONAL RIGHT OF WAY FOR SHOREY ROAD BANK STABILIZATION M.P. 0.598
WHEREAS, permanent bank stabilization of Shorey Road is necessary due to 2021 flood damage; and
WHEREAS, the stabilization of the road will require additional right of way from one adjacent property owner; and
WHEREAS, this project is a necessary improvement and will benefit the public; and
WHEREAS, this resolution instructs the County Engineer to acquire additional road right of way as shown on the attached Exhibit, from one property owner along Shorey Road for the project.
NOW THEREFORE BE IT RESOLVED that the County Engineer is instructed to acquire all necessary right of way and is authorized to sign documents necessary for the stabilization of Shorey Road in Section 31, Township 14 North, Range 2 West, W.M. and Section 6, Township 13 North, Range 2 West, W.M., and directs that the acquisition be in accordance with adopted procedures as per Resolution 20-149.
DONE IN OPEN SESSION this 28th day of November, 2023.