Summary:Approving a Task Assignment pursuant to Interlocal Agreement No. 05-200 between Lewis County and Tacoma Power regarding work by county crews and authorizing signatures thereon
Publications:
Cover Letter To: Please send a fully executed original of the agreement to: Tacoma Power, Attn: Stephen Fairchild, 3628 South 35th Street, PO Box 11007, Tacoma, WA, 98411-0007
Additional Copies To: Tim Fife - PW Mike Kroll - PW Tina Hemphill - PW Robin Saline - PW Kevin Korpi - PW Mike Kroll - PW
Resolution
APPROVE A TASK ASSIGNMENT PURSUANT TO INTERLOCAL AGREEMENT NO. 05-200 BETWEEN LEWIS COUNTY AND TACOMA POWER REGARDING WORK BY COUNTY CREWS AND AUTHORIZE SIGNATURES THEREON
WHEREAS, pursuant to the authority of RCW 39.34.080 and in conformance with RCW 43.09.210, Lewis County entered into Interlocal Agreement 05-200 dated July 18, 2005, to perform identifiable maintenance and construction tasks including road construction and maintenance; and
WHEREAS, at the request of Tacoma Power and pursuant to the approved Interlocal Agreement, the Public Works Director and County Engineer have reviewed a task assignment (Exhibit A) and recommend that the Board of County Commissioners (BOCC) approve Task Assignment #2023-01 between Lewis County and Tacoma Power regarding maintenance work to be performed by county crews; and
WHEREAS, Task Assignment #2023-01 is for chipseal and traffic striping work, at an estimated cost of $71,937.33, which includes labor, materials, and equipment, plus an administrative fee of $3,596.87, for a total of $75,534.20.
NOW THEREFORE BE IT RESOLVED that the BOCC has determined proceeding with Task Assignment #2023-01 is in the best public interest and is hereby approved, and the BOCC is authorized to sign the same.