Directors' Update: March 1, 2023
Business Meeting: March 7, 2023
Summary:This resolution will ratify a consultant agreement in the amount of $200,000 for professional design and engineering services for water crossing structures with HDR Engineering, Inc.
Publications:
Cover Letter To:
Additional Copies To: Geoff Soderquist, PW; Ann Weckback, PW; Robin Saline, PW; Tina Hemphill, PW; Shayla Landon PW
Resolution
RATIFY A CONSULTANT AGREEMENT FOR $200,000 FOR ANNUAL DESIGN AND ENGINEERING SERVICES FOR WATER CROSSING STRUCTURES WITH HDR ENGINEERING, INC.
WHEREAS, pursuant to Resolution 21-038, approval from the Board of County Commissioners (BOCC) is required for all contracts, projects, agreement, grant applications, contract amendments and change orders involving expenditures totaling between $50,000 and $200,000; and
WHEREAS, A Request for Proposals was published on November 3 and 10, 2022, to solicit submittals from consultants with expertise in professional design and engineering services for water crossing structures. Lewis County Public Works does not have the required resources to complete this work within the scheduled time; and
WHEREAS, on February 15, 2023, the Director of Public Works approved an Annual Consultant Agreement with HDR Engineering, Inc. for professional design and engineering services for water crossing structures. The agreement was for a maximum amount payable of $200,000.
NOW THEREFORE BE IT RESOLVED that the BOCC hereby approves the Consultant Agreement previously executed by the Public Works Director.
DONE IN OPEN SESSION this 7th day of March, 2023.