Logan Hill Road at MP 0.103 at Berwick Creek requires a channel realignment and culvert replacement. The project will require additional property rights from one adjacent property owner.  This resolution instructs the County Engineer to acquire the necessary right of way from one property owner along Logan Hill Road for the project.  The acquisition shall be in accordance with adopted procedures as per Resolution 20-149.

Publications:

Cover Letter To:

Additional Copies To: Tim Fife, Shawn Kyes, Tina Hemphill

Resolution

Wording/In the matter of:

THE PROPOSED ACQUISITION OF ADDITIONAL RIGHT OF WAY FOR LOGAN HILL ROAD IN CHEHALIS

Resolution Number: 22-216

WHEREAS, Logan Hill Road MP 0.103 at Berwick Creek requires a culvert replacement; and

WHEREAS, the project will require additional property rights from one adjacent property owner; and

WHEREAS, the project is a necessary improvement and will benefit the public; and

WHEREAS, this resolution instructs the County Engineer to acquire the property rights as shown on the attached exhibit from one property owner along Logan Hill Road for the project.

NOW THEREFORE BE IT RESOLVED that the County Road Engineer is instructed to acquire all necessary right of way and is authorized to sign documents necessary for the culvert replacement project on Logan Hill Road in Section 11, Township 13 North, Range 2 West, W.M.; and

NOW THEREFORE BE IT FURTHER RESOLVED that the BOCC directs that all such acquisitions be in accordance with adopted procedures as per Resolution 20-149.