Information
Type: Deliberation
Department: PW - Public Works
Directors' Update: Sept. 8, 2021
Business Meeting: Sept. 14, 2021
Summary:This resolution will approve an increase over $200,000 to the Tucker Road Improvement Project, County Road Project No. 2189-C for additional paving funded by federal grant funds.
Publications:
Cover Letter To:
Additional Copies To: Tina Hemphill, PW, Tim Fife, PW, Geoff Soderquist, PW, Robin Saline, PW, Sadie Rockey, PW, Matt Hurley, PW
Resolution
APPROVING A CONTRACT INCREASE OVER $200,000 FOR A PUBLIC WORKS PROJECT
WHEREAS, pursuant to Resolution 21-038, the Board of County Commissioners' (BOCC) approval is required for all contracts, projects, agreement, grant applications, contract amendments and change orders involving expenditures in excess of $200,000; and
WHEREAS, the BOCC approved Resolution 20-302 awarding the Tucker Road Improvement project, Federal Aid Project No. STPR-F212(001) F.A. Agreement No. TA-6968, CRP 2189-C to Granite Construction in the amount of $511,170.00; and
WHEREAS, On July 9, 2020, Agreement #LA 9901 was executed between Lewis County and Washington State Department of Transportation awarding $700,000 for the Tucker Road Improvement Project; and
WHEREAS, on October 12, 2020, the Assistant County Engineer approved a Change Order for the Tucker Road Improvement Project, CRP 2189C to include an additional 1.5 miles of paving, 24 feet wide by 1.5 feet deep as described in section 5-04 of the Contract Special Provisions, at an estimated cost of $270,326.88; and
WHEREAS, the final contract amount of the Tucker Road Improvement Project, CRP 2189-C, is $742,709.85, an increase of $231,539.85.
NOW THEREFORE BE IT RESOLVED that the BOCC finds the additional paving to be in the best interest of the public and approves the increase of $231,539.85 to the final contract for the Tucker Road Improvement Road project, CRP 2189-C.
DONE IN OPEN SESSION this 14th day of September, 2021.