Information
Type: Deliberation
Department: PW - Public Works
Directors' Update: June 16, 2021
Business Meeting: June 22, 2021
Summary:Approving a Task Assignment pursuant to Interlocal Agreement No. 05-200 between Lewis County and Tacoma Power regarding work by county crews and authorizing signatures thereon
Publications:
Cover Letter To: Please send a fully executed original of the agreement to: Tacoma Power, Attn: Stephen Fairchild, 3628 South 35th Street, PO Box 11007, Tacoma, WA, 98411-0007
Additional Copies To: Tim Fife - PW Tina Hemphill - PW Robin Saline - PW Kevin Korpi - PW
Resolution
APPROVING A TASK ASSIGNMENT PURSUANT TO INTERLOCAL AGREEMENT NO. 05-200 BETWEEN LEWIS COUNTY AND TACOMA POWER REGARDING WORK BY COUNTY CREWS AND AUTHORIZING SIGNATURES THEREON
WHEREAS, pursuant to the authority of RCW 39.34.080 and in conformance with RCW 43.09.210, Lewis County entered into Interlocal Agreement 05-200 dated July 18, 2005, to perform identifiable maintenance and construction tasks including road construction and maintenance; and
WHEREAS, at the request of Tacoma Power and pursuant to the approved Interlocal Agreement, the Public Works Director and County Engineer have reviewed a task assignment (Exhibit A) and recommend that the Board of County Commissioners (BOCC) approve Task Assignment #2021-01 between Lewis County and Tacoma Power regarding maintenance work to be performed by county crews; and
WHEREAS, Task Assignment #2021-01 is for chipseal work, at an estimated cost of $30,066.67, which includes labor, materials, and equipment, plus an administrative fee of $1,503.33, for a total of $31,570.00.
NOW THEREFORE BE IT RESOLVED that the BOCC has determined proceeding with Task Assignment #2021-01 is in the best public interest and is hereby approved, and the BOCC is authorized to sign the same.
DONE IN OPEN SESSION this 22nd day of June, 2021.